REGULATORY AGENCIES CLEAR GKN AEROSPACE FOR MMA OPERATIONS FOLLOWING SAFETY UPGRADES
GKN Aerospace (GKN) has received the required agency clearances to resume manufacturing using methyl methacrylate (MMA) from Tank 4 at its Garden Grove facility. The City does not have a confirmed restart date.
Of the three MMA tanks at GKN’s Garden Grove facility, only Tank 4 is covered by the clearances. Tank 1, which was involved in the May 21, 2026, hazardous materials incident, remains out of service. Tank 2, which was not involved in the incident, also remains out of service. The City of Garden Grove, Orange County Fire Authority, OC Health Care Agency, South Coast Air Quality Management District, Orange County Sanitation District, Cal/OSHA and the Department of Toxic Substances Control each confirmed that GKN met the restart requirements within their respective jurisdictions.
“Our responsibility to protect residents and workers does not end with these clearances,” said Garden Grove Mayor Stephanie Klopfenstein. “The City will continue to hold GKN accountable for complying with all applicable safety requirements.”
Work on Tank 4 included weld repairs, third-party inspections of the tank and its welds, and successful leak testing. GKN also upgraded the tank’s connections, valves, piping and structural components, repaired or replaced parts of the pressure-relief system, and restored the chemical inhibitor system.
“The Orange County Fire Authority has worked closely with the City of Garden Grove and other regulatory agencies throughout this process to ensure applicable fire and life safety requirements within our jurisdiction have been met,” said TJ McGovern, Fire Chief of the OCFA. “Our focus remains on community safety, and we will continue coordinating with our partner agencies.”
To improve monitoring and emergency response, the company installed additional equipment to track temperature, pressure and liquid levels, upgraded alarms and revised emergency procedures.
Since May, City staff have visited the facility, and met with GKN on repairs, testing and safety upgrades as part of the City’s compliance work. GKN must continue to comply with applicable City requirements and the court-approved safety plan, which requires independent monitoring and annual audits. Garden Grove will continue to enforce its own requirements and coordinate with its regulatory partners.
The City of Garden Grove will continue sharing verified information about the claims program and safety requirements at wwww.ggcity.org/hazmat-incident. For GKN updates and to sign up for notifications, visit www.gkngg.com.