Sewer System Rehabilitation Plan Phase I Sewer Main Lining and Spot Repair Projects 5 & 6

I’m with ConstructConnect. I am writing to ask for the awarded contractor and awarded amount for the above project. I would also like to know the anticipated start dates, if determined.

If you’re not familiar with ConstructConnect and would like to know why we collect this data, schedule a time to speak with my manager Patrick Quarry. He can show you our website and answer any questions. Click Here to check his schedule and select a time that works best for you.

Correspondence

Request has been completed.
December 08, 2023
Message from Amanda M Pollock

Awarded contractor: Tunnelworks Services Inc.
Awarded amount: $1,784,125.00
Anticipated start dates: Jan 15, 2024