Noticing Traffic increased on Brookhurst south bound between Trask and Woodbury, this during daytime hours. Has the traffic light timing changed or not synchronized correctly. Takes around 15 mins for this crossover.

Correspondence

Message from Muhammad Aslam

Thank you for the prompt response. The construction completed last weekend however the traffic congestion has continued since, even today. I hope there is a resolution soon as this is causing a lot of frustration to commuters.

August 29, 2019
Request has been completed.
August 29, 2019
Message from Maritza Pizarro

Per Garden Grove Traffic Engineering, the City modified the traffic signal at Brookhurst and Woodbury/Traylor to add left turn phasing on Woodbury/Traylor the week of August 22nd. There may have been increased congestion due to the construction. The work is complete and staff is monitoring the intersection to fine tune the traffic signal timing.

Thank you,
Maritza Pizarro
Records Coordinator
City Clerk's Office
City of Garden Grove
714-741-5039

August 29, 2019
Assigned to Dai C Vu, Rosemarie Jacot
August 28, 2019
Request received
August 28, 2019

 

Closed on Aug 29
Respond