Request #1540
PUBLIC
The contract amount and the timeline for the Palm Neighborhood Slurry Seal Project.
Correspondence
Request has been satisfied.
January 25, 2016
Message from Denise Kehn
January 25, 2016
Assigned to Robert R Moungey
January 13, 2016
Request received
January 13, 2016
Closed on Jan 25
Dear Ms. Lambert,
Attached is the cost breakdown for the Palm Neighborhood Slurry Seal Project. The timeline for the project was September 22 thru November 16, 2015, with a total of approximately 272 man hours. This number includes removals, patching, grinding weeding edges, crack sealing slurry and inspections.
Sincerely,
Denise Kehn
Records Specialist
City of Garden Grove